GM Powertrain Group
Tonawanda Engine Plant
Medical Department
- Relocation / Rehabilitation
This project involved relocation and renovations to the existing Medical
Department at the world's largest Engine Plant. The project required
coordination of numerous separate prime contracts including relocatable wall
system vendors, General Construction contractors, hazardous materials
contractors and several separate engineering groups.
GM Powertrain required the drawings to be completed and
out to bid in less than three weeks from project approval. We were also
required to coordinate temporary facilities for occupancy during the 8 week
construction phase of the project.
Metrology Lab Relocation
This project involved the construction of 4,000 sf of office and lab space
to accommodate the relocation of the existing Metrology Lab within the
confines of the existing plant.
Successful design and execution of the project involved
extensive on-site documentation and design revision in order to fit the many
constraints of the program: vibration isolation for gage equipment to
0.0001" accuracy, supply of a clean air environment within the existing
Engine Plant and limited space within the plant. Restrictions in the
footprint of the labs led to the design of office space and an equipment
mezzanine within the confines of the intersecting roof trusses. |